International Project Management Association (IPMA) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the International Project Management Association Exam with a quiz. Test your skills with flashcards and multiple choice questions. Enhance your study with detailed explanations and hints. Ace your certification!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Resource leveling is likely to?

  1. Increase the most likely project cost

  2. Increase the most likely duration of the project

  3. Have little or no effect on individual activity durations

  4. Have little or no effect on the overall project durations

The correct answer is: Increase the most likely duration of the project

Resource leveling aims to address resource allocation by redistributing tasks to minimize peaks in resource utilization while avoiding overloading resources. This often involves delaying activities that can be postponed without affecting the project's overall objectives. By leveling resources, it can result in the extension of the project timeline because tasks might need to be scheduled later to accommodate the availability of resources. Consequently, when critical resources are spread more evenly over the project timeline, some activities may take longer to complete or may start later than they would have under a more aggressive schedule. Therefore, when resource leveling practices are applied, it is common for the project duration to increase as tasks are shifted to balance resource demands. This understanding highlights the potential impact of resource leveling on project timeline and emphasizes the importance of effective resource management in project planning.