International Project Management Association (IPMA) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the International Project Management Association Exam with a quiz. Test your skills with flashcards and multiple choice questions. Enhance your study with detailed explanations and hints. Ace your certification!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which factor can significantly affect project scope management?

  1. The skills of the project manager

  2. The clarity of stakeholder expectations

  3. The availability of resources

  4. The project funding type

The correct answer is: The clarity of stakeholder expectations

The clarity of stakeholder expectations is a critical factor that can significantly affect project scope management. When stakeholder expectations are clearly defined and understood, it provides a solid foundation for establishing project goals, objectives, and deliverables. Clarity in expectations helps to ensure that all stakeholders are aligned on what the project is intended to achieve, thereby reducing the likelihood of scope creep, where additional requirements are added without proper evaluation. When stakeholders communicate their needs and expectations effectively, it leads to better planning and execution, as the project team can develop a more accurate project scope. Additionally, it fosters a collaborative environment where adjustments can be made proactively, preventing misunderstandings that can derail a project. By focusing on stakeholder clarity, project managers can create a well-defined scope statement and use it as a reference point throughout the project lifecycle to ensure that all changes are controlled and managed appropriately. This ultimately enhances the chances of delivering the project successfully within the agreed constraints.